War Memorial upgrade blasted in report

A scathing report into the Australian War Memorial’s $550 million upgrade has revealed conflicts of interest, contract irregularities and cost blow-outs.

Apr 12, 2024, updated Apr 12, 2024
Trench art featured in an Australian War Memorial collection. Photo: Paul Steed

Trench art featured in an Australian War Memorial collection. Photo: Paul Steed

An Auditor-General’s report into the Canberra-based institution found conflicts of interest were not adequately documented or declared and that contracts had been split so they would not need ministerial approval.

It also revealed then-prime minister Scott Morrison – who makes a final bow from politics on Saturday when voters choose a new member for his seat – had approved the project before its business case was finalised.

There was “no evidence” it had been considered by government before the controversial upgrade was announced in 2018, the report said.

On Wednesday, a spokesperson for Veterans’ Affairs Minister Matt Keogh said he was concerned by the revelations.

“The minister has requested an urgent briefing by the ANAO (Australian National Audit Office) on its findings and recommendations, and will discuss these with the Australian War Memorial’s management as a priority,” they said.

Opposition veterans’ affairs spokesman Barnaby Joyce said a business case should not take priority over sacrifice.

“We say ‘Lest we Forget’: we have never said ‘Lest we Forget, dependent on a business case’,” he said.

“While the auditor has identified important improvements for better processes and ministerial oversight, I am supremely relaxed that our government made the decision to announce the project before a business case had been completed.

“I am uncomfortable when the words ‘business case’ and ‘remembering them’ are used in the same sentence – very uncomfortable.

InDaily in your inbox. The best local news every workday at lunch time.
By signing up, you agree to our User Agreement andPrivacy Policy & Cookie Statement. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

“We didn’t send our fine men and women to war based on a business case, they didn’t die and get shot-up based on a business case, and we shouldn’t decide whether we remember them or not, based on a business case.”

The Australian War Memorial’s multimillion dollar upgrade set for completion in 2028 has been mired in controversy from the outset.

Though it is expected to increase visitor space by 83 per cent, Anzac Hall will be knocked down and rebuilt despite having only been opened in 2001 at a cost of $17 million.

The auditor-general’s report revealed one contract with Xact Project Consultants had been varied to $999,999 – one dollar below the threshold required for ministerial approval.

Another contract with Imagination (Australia) Pty Ltd worth $1.05 million was split into two, one worth $841,875.43 and the other $207,659.10.

Both were signed the same day.

The auditor-general made five recommendations including that the memorial improve its records management policies and strengthen the ethical conduct of procurement – all of which have been agreed or agreed in principle.

– AAP

Topics: war memorial